Pipeline · Permitting

Buffalo Lick Solar + Storage

6 MW-AC solar with 5 MW / 4-hour storage on about 40 acres in Greene County, Georgia. Saga's first Georgia project: permitting underway, interconnection feasibility complete, and a bid into Georgia Power's DG RFP.

Greene County, GA Georgia Power SERC Target COD 2027-Q4
Solar MW-AC
6
BESS MW
5
BESS MWh
20
Status as of
July 17, 2026

Site

About 40 acres leased from a private landowner in Greene County, Georgia. The layout is set inside the county setback requirement and routed around the NWI-mapped wetlands on the parcel. This is Saga’s first project in Georgia.

Interconnection

Distribution-level interconnection on Georgia Power’s system. The interconnection feasibility study is complete.

Offtake

Submitted into Georgia Power’s distributed generation (DG) RFP.

Permitting

County permitting pre-application is complete.

Status