Pipeline · Permitting
Buffalo Lick Solar + Storage
6 MW-AC solar with 5 MW / 4-hour storage on about 40 acres in Greene County, Georgia. Saga's first Georgia project: permitting underway, interconnection feasibility complete, and a bid into Georgia Power's DG RFP.
Greene County, GA Georgia Power SERC Target COD 2027-Q4
- Solar MW-AC
- 6
- BESS MW
- 5
- BESS MWh
- 20
- Status as of
- July 17, 2026
Site
About 40 acres leased from a private landowner in Greene County, Georgia. The layout is set inside the county setback requirement and routed around the NWI-mapped wetlands on the parcel. This is Saga’s first project in Georgia.
Interconnection
Distribution-level interconnection on Georgia Power’s system. The interconnection feasibility study is complete.
Offtake
Submitted into Georgia Power’s distributed generation (DG) RFP.
Permitting
County permitting pre-application is complete.
Status
- About 40-acre site under lease
- 6 MW-AC solar paired with 5 MW / 4-hour BESS (20 MWh)
- Interconnection feasibility study complete
- Submitted to Georgia Power’s DG RFP
- County permitting pre-application complete
- NTP Q2 2027, COD end of 2027